Update on Cristo Rey Church
This is an update from the Architect of the building progress at Cristo Rey Church. As a point of reference, our Sheridan team from July dug the footings for these walls. You can read about their experiences here.
Thanks for always remaining interested in the construction progress of the Temple of Cristo Rey Church in Santa Ana. I write to inform you of the progress of the project up to September 15, 2014:
• The foundation construction process (i.e. the digging & footings with rebar) has been 100% completed at Cristo Rey, this represents 20% of overall project progress
• The process of building concrete block walls has started. After this process is finished, the project will be 50% complete.
Below are some updated photographs from September 15.
Best regards,
Carlos Coto, Project Architect

