Update on Cristo Rey Church

ElSalvador_09_15_2014-back-right-looking-left

This is an update from the Architect of the building progress at Cristo Rey Church. As a point of reference, our Sheridan team from July dug the footings for these walls. You can read about their experiences here.

Thanks for always remaining interested in the construction progress of the Temple of Cristo Rey Church in Santa Ana. I write to inform you of the progress of the project up to September 15, 2014:
• The foundation construction process (i.e. the digging & footings with rebar) has been 100% completed at Cristo Rey, this represents 20% of overall project progress
• The process of building concrete block walls has started. After this process is finished, the project will be 50% complete.

Below are some updated photographs from September 15.

Best regards,
Carlos Coto, Project Architect

ElSalvador_09_15_2014 (back right looking left)

Start of day, bricks about to be laid.

ElSalvador_09_15_2014 (back middle looking right2)

Bricks for the walls are being laid.

ElSalvador_09_15_2014 (back middle looking right)

Additional view of progress for the day.